Phase Entry and Exit Checklists

Discovery Entry Checklist

  • Sponsor identified

  • Problem or opportunity described

  • Discovery timebox agreed

  • Commercial authority confirmed

  • Stakeholder access agreed

  • Research access agreed

  • Security constraints identified

  • Evidence repository created

Discovery Exit Checklist

  • Problem statement completed

  • User needs identified

  • Current state mapped

  • Constraints recorded

  • Risks and assumptions recorded

  • Options assessed

  • Recommendation prepared

  • Alpha or next-phase scope drafted

  • Decision recorded

Alpha Entry Checklist

  • Discovery recommendation approved

  • Alpha questions agreed

  • Riskiest assumptions ranked

  • Team roles confirmed

  • Prototype approach agreed

  • Technical spike plan created

  • Security and data constraints understood

  • Commercial authority confirmed

Alpha Exit Checklist

  • Prototypes tested

  • User feedback captured

  • Technical feasibility assessed

  • Security and data implications understood

  • Preferred option selected

  • Beta backlog created

  • Beta roadmap drafted

  • Commercial assumptions updated

  • Proceed, stop or reshape decision recorded

Beta Entry Checklist

  • Beta Statement of Work agreed

  • Backlog prioritised

  • Acceptance criteria agreed

  • Environments planned

  • Engineering standards confirmed

  • Security approach confirmed

  • Release approach agreed

  • Support model design started

Beta Exit Checklist

  • Critical journeys tested

  • Service or product working for real users

  • Security evidence complete or risk-accepted

  • Accessibility evidence complete where required

  • Performance evidence reviewed

  • Support model ready

  • Monitoring in place

  • Live readiness approved

  • Acceptance recorded

Live Entry Checklist

  • Service owner confirmed

  • Support process live

  • Monitoring active

  • Incident process agreed

  • Access controls reviewed

  • Operational documentation complete

  • Release process agreed

  • Service metrics agreed

Live Review Checklist

  • Service performance reviewed

  • User feedback reviewed

  • Support tickets reviewed

  • Incidents reviewed

  • Security vulnerabilities reviewed

  • Improvement backlog prioritised

  • Technical debt reviewed

  • Roadmap updated

Retirement Entry Checklist

  • Retirement trigger identified

  • Service owner engaged

  • User impact assessed

  • Data impact assessed

  • Supplier impact assessed

  • Contractual exit obligations reviewed

  • Retirement approval route agreed

Retirement Exit Checklist

  • Users informed or transitioned

  • Data retained, migrated, archived or deleted

  • Access removed

  • Integrations closed

  • Suppliers exited

  • Redirects implemented where required

  • Service decommissioned

  • Closure evidence stored

  • Final approval recorded